City of Dawson

Construction Updates

June 28, 2010

Construction Drilling Inc. is on site and grouting of the pre-grout holes is underway. Corix requested a waiver on the noise bylaw from Town Council to allow for work to take place around the clock in order to hasten this task and keep the overall project on schedule. Town Council has approved this waiver and the target for completion of this work is slated for sometime in early July.

Drilling of the main shafts is expected to begin in mid July and construction of the facility is still slated for the fall.